As part of The Lau Hala Shops renovation, a parking lot seal coat and restriping project is set to start on Monday, July 30, 2018. The project will be split up into three phases, only affecting one parking lot section at a time.

As always, please pay attention to ongoing construction work and be aware of your surroundings to ensure safe access for pedestrians and drivers around the construction area. Additional customer parking will be available inside the parking garage, 2nd floor throughout construction.

Monday, July 30 – Wednesday, August 1
Phase 1: Beginning on asphalt closest to the parking structure. Work area in red will be closed off.  Remainder of parking lot (except bus staging area) will remain open.

Monday, August 6 – Wednesday, August 8
Phase 2: Middle section of open parking lot. Work area in green will be closed off. Remainder of parking lot (except bus staging area) will remain open.

Monday, August 13 – Wednesday, August 15
Phase 3: Parking lot section closest to Hahani Street. Work area in orange will be closed off. Remainder of parking lot (except bus staging area) will remain open.

 